Challenge

Before the project, production quality was tracked in Excel. With 15 machines across 6 lines and a lean team of five operators, the lack of real‑time insights meant defective products could leave the factory, leading to penalties. The client needed immediate defect detection and end‑to‑end traceability for every part.

Solution

We started with a pilot on one line to validate the flow, then expanded to all lines after sign‑off.

Results

Technologies

Rollout & Support

Pilot: 3 months of development and testing on a single line. Full rollout: additional 3 months to cover all lines and machines. Ongoing support: continuous statistics, data analysis, and iterative enhancements.